Boeddeker Park - Under Construction
Credit: TPL Archive
For questions or comments about the playground, please contact Alejandra Chiesa or 415.800.5303
The Friends of Boeddeker Park community meetings are held at 3:30 p.m. on the third Thursday of the month. Contact Betty Traynor for location information.
See the latest photos of the park's construction on our Facebook page.
May 2013 | What is happening
- Construction of the building foundation including drilled piers
- Continue building of wooden forms into which concrete will be poured to create site walls
- Continue pouring concrete walls on Ellis St. side of the Park
June 2013 | What to expect
- Pour concrete for stairs and pavement on Ellis St. side of the Park
- Continue work on the Clubhouse building
- Drilling 250 feet deep into bedrock for the geothermal loop for part of the energy efficient heating and cooling system for the building
- Work on Eddy Street to connect to PG&E utility vault