Boeddeker Park - Under Construction
Credit: TPL Archive
For questions or comments about the playground, please contact Alejandra Chiesa or 415.800.5303
The Friends of Boeddeker Park community meetings are held at 3:30 p.m. on the third Thursday of the month. Contact Betty Traynor for location information.
See the latest photos of the park's construction on our Facebook page.
March 2013 | What is happening
- Excavation at the site of the new clubhouse and underground utilities
- Leveling and compacting ground where walls, amenities, and paths will be built
- Building of wooden forms into which concrete will be poured to create site walls
- Starting to pour concrete walls on Ellis Street side of the Park
April 2013 | What to expect
- Continue leveling and compacting ground where walls, amenities, and paths will be built on Eddy St. side of the Park
- Continue building wooden forms and pouring concrete for site walls
- Start work on the clubhouse building foundation